A-Tension
- DP Event
- Published on 16 January 2025
- Generated on 8 May 2025
- DPE 01/25
- 3 minute read
1 Overview
The DP equipment class 3 pipelaying vessel (s-lay) was operating in open bus in a two way split configuration, with all thrusters and generators online. There were four DGNSS selected to DP, however no further position reference systems were selected. Two tensioners set on tension mode provided set-point and load cell feedback to the DP system in order to update the mathematical model.
2 What happened?
Whilst pipelaying in shallow water, the vessel experienced a tension sensor failure on one tensioner. An alarm for sensor failure was generated on DP when the tensioner sensor failed and the DP system stopped receiving measured tension.
At this point the tension load was transferred to the remaining on-line tensioner.
Six minutes later the second tensioner experienced the same fault on the load cell and went offline. Now with no tensioner inputs to the DP system, the tension mode was lost and the tensioners applied the brake.
The sudden force applied by the pipe tension caused the vessel to become unstable and the vessel lost position, exceeding the allowable pipe integrity and causing damage to the pipe.
3 Findings
Troubleshooting of the event concluded that:
-
When the first tension sensor failed, the tensioner went off line and the Event Handling feature applied a fixed calculated value (estimated value). A correct tension value is vital information when laying in shallow water.
-
The investigation found that the DP Personnel had insufficient knowledge on the role of the tension sensors and the critical nature of the situation if the tensioners are no longer in tension mode.
-
Due to multiple failures causing different warnings and alarms, the DPO did not act accordingly.
4 Conclusion
Training, training, training. Mechanical failures happen and that is a fact, how we respond to them is based on knowledge and preparedness.
It was not immediately apparent to the personnel present on the Bridge that the tensioners were no longer in tension mode and the DPO was unaware of the critical nature of the situation.
The action that was required in this situation was to minimise the vessels surge motions by applying a fixed input as a manual force along the surge axis to try and maintain the adequate tension on the pipe.
Since the incident the company implemented multiple upgrades in hardware and training:
-
Two additional lights installed on the Bridge to alert DPO and personnel on the Bridge if a sensor fails or the tensioner goes on the brake.
-
Additional screen to check tensioner alarm page (On Tensioner/A&R Winch Console), for easier reference
-
The company released a new document, a guideline for S-Lay operations in shallow water.
-
This is aimed at providing guidance and information to their DPOs, informing them of the correct action to be taken in the event of sensor failure.
-
DP Drill Plan amended to include the incident scenario and improve familiarisation of DPOs alongship force control.
The following IMCA Guidance would be relevant to these case studies:
-
IMCA M117 – Code of practice for the training and experience of key DP personnel
-
IMCA M166 – Code of practice on Failure Mode and Effects Analysis (FMEA)
-
IMCA M220 – Guidance on operational planning
-
IMCA M247 – Guidance to identify DP system components and their failure modes
-
IMCA M252 – Guidance on position reference systems and sensors for DP operations
-
IMCA Information Note No.1634 – Increasing solar activity and the effect on GNSS positioning
-
IMCA Information Note No.1650 – Important PRS considerations when operating close to an asset that is not rigidly fixed to the seabed
Latest DP incidents
-
Complete the job
Whilst connected to a turbine, an alarm was generated on the DP operator station, ‘Unbalanced load on SWBD 1’.
DPE 01/25
16 January 2025
Undesired event
-
Beware your centre of rotation
The stern thrusters started to oscillate which transferred to an oscillating motion of the vessel and high forces were being used to try to maintain position.
DPE 01/25
16 January 2025
Incident
-
A-Tension
Whilst pipelaying in shallow water, the vessel experienced a tension sensor failure on one tensioner.
DPE 01/25
16 January 2025
-
How is your alignment?
Loss of the CyScan position reference system generated a reference system failure alarm and moments later the vessel began to lose position with the accompanying alarms.
DPE 01/25
16 January 2025
Incident
-
DP Drill Scenario
DP emergency drill scenarios are included to assist DP vessel management, DPOs / Engineers, and ETOs in conducting DP drills onboard.
DPE 01/25
16 January 2025
Drill Scenario
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.