Leak in fuel supply line causes engine to shut down
- DP Event
- Published on 29 May 2018
- Generated on 9 May 2025
- DPE 02/18
- 2 minute read
Undesired event
Jump to:
A fuel leak developed in a corroded supply pipe to the port main engine. This caused air to be drawn into the system and the engine to shut down.

Comments
The vessel was employed within the renewable energy sector, no details were given of the drilling activities.
A fuel leak developed in a corroded supply pipe to the port main engine. This caused air to be drawn into the system and the engine to shut down.
Redundancy worked as designed. The split fuel system ensured that only the port side of the engine room was affected and operations were suspended due to loss of redundancy.
Considerations
- It was noted that three DGNSS were selected to DP; clearly this is not in accordance with DP equipment class 2 that requires position reference systems to have at least two different principles of operation.
- The vessel was operating closed bus and while the failure did not exceed the vessel’s designed worst case, a different fault on the electrical system may have resulted in a more significant DP system failure.
- Water depth of 45m only provides a small envelope of operation.
- Actions taken in response to the failure appear to be appropriate and in line with good practice.
- The planned maintenance system (PMS) for critical piping systems should be reviewed. For an F.O. supply line to fail due to corrosion should warrant complete inspection of the rest of the system, and a review of past inspections/maintenance so that similar faults are not missed in the future.
Latest DP incidents
-
Complete the job
Whilst connected to a turbine, an alarm was generated on the DP operator station, ‘Unbalanced load on SWBD 1’.
DPE 01/25
16 January 2025
Undesired event
-
Beware your centre of rotation
The stern thrusters started to oscillate which transferred to an oscillating motion of the vessel and high forces were being used to try to maintain position.
DPE 01/25
16 January 2025
Incident
-
A-Tension
Whilst pipelaying in shallow water, the vessel experienced a tension sensor failure on one tensioner.
DPE 01/25
16 January 2025
-
How is your alignment?
Loss of the CyScan position reference system generated a reference system failure alarm and moments later the vessel began to lose position with the accompanying alarms.
DPE 01/25
16 January 2025
Incident
-
DP Drill Scenario
DP emergency drill scenarios are included to assist DP vessel management, DPOs / Engineers, and ETOs in conducting DP drills onboard.
DPE 01/25
16 January 2025
Drill Scenario
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.