Uncontrolled decompression of diving bell

  • Safety Flash
  • Published on 1 December 2004
  • Generated on 13 December 2024
  • IMCA SF 10/04
  • 3 minute read

A member has reported an incident involving the uncontrolled decompression of a submersible decompression chamber (SDC) during diving operations. 

What happened?

The three man bell vented to surface from 175 fsw when the last man leaving accidentally kicked open a ¼-turn valve. Thinking that a seal had been lost, he immediately continued through the man-way to the TUP and secured the door behind him. The valve was located on the bottom inner door and was not accessible from the outside as the outer bottom door was in the closed position. The bell was allowed to vent to surface as the decompression occurred at a rapid enough rate such that it was deemed inadvisable to try and ‘catch’ the leak with the addition of more gas. There were no injuries or equipment damage reported.

Elements contributing to the incident according to the first report are listed as:

  • the valve having been the wrong type and size.
  • previous man-way sealing problems which initiated the assumption that the source of the leak was in the man-way. This in turn prompted a hasty retreat through to the TUP.

    The immediate action was to remove the handle from the stem to avoid a recurrence. Subsequently the oversized ¼-turn ball valve was replaced with a small bore needle valve to affect a permanent solution.

    Sealing problems due to misalignment were evident at the initial stages of the mobilization when the system was being function tested onboard the diving support vessel. Several modifications to the skid and clamping device had to be made prior to achieving a successful pressure leak test. The system was a recent rebuild and the project was the first one for its current configuration.

    Had the valve been kicked open with three men inside prior to opening the door to the TUP, the consequences could have been dire. The combination of the crowded circumstance, the possible loss of visibility from the condensation build up and the focus on a leak anticipated in another area of concern (the man-way) would have made a controlled response very unlikely

The company has summarised the key issues as follows:

  • The valve originally installed was not suitable for purpose in terms of both size and type.
  • The testing and commissioning of a new or re-build system should be completed prior to its installation on a project vessel.
  • System familiarisations and drills should note and highlight the most likely sources of potential leaks – in this case the bottom door hatch (this is the rationale behind the double valve arrangement of a bell flood up valve).
  • Caution should always accompany movements within confined spaces.

Latest Safety Flashes:

LTI: Finger injury during emergency recovery of ROV

A worker suffered a serious finger injury when their finger was caught between a crane wire and the recovery hook on an ROV.

Read more
BSEE: recurring hand injuries from alternative cutting devices

The United States Bureau of Safety and Environmental Enforcement (BSEE) has published Safety Alert 487.

Read more
NTSB: Crane wire failure

The National Transportation Safety Board of the United States (NTSB) published "Safer Seas Digest 2023".

Read more
Hot work performed outside of Permit to Work (PTW) boundary limit

A near miss occurred when a third-party contractor working removed a trip hazard from the vessel main deck, using a cutting torch and grinding disc.

Read more
Vital safety information (height of vehicle) found incorrect

“Height of vehicle” information displayed on a truck, was found to be incorrect.

Read more

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of the entire offshore industry.

The effectiveness of the IMCA Safety Flash system depends on the industry sharing information and so avoiding repeat incidents. Incidents are classified according to IOGP's Life Saving Rules.

All information is anonymised or sanitised, as appropriate, and warnings for graphic content included where possible.

IMCA makes every effort to ensure both the accuracy and reliability of the information shared, but is not be liable for any guidance and/or recommendation and/or statement herein contained.

The information contained in this document does not fulfil or replace any individual's or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.

Share your safety incidents with IMCA online. Sign-up to receive Safety Flashes straight to your email.