High potential near-miss – Lifting equipment failure

  • Safety Flash
  • Published on 25 June 2013
  • Generated on 6 December 2024
  • IMCA SF 10/13
  • 3 minute read

A Member has reported an incident in which there was a potentially catastrophic failure of a lifting sling. 

What happened?

The incident occurred during repair and maintenance operations for a trenching ROV, when the trencher was being lifted onto axle stands to assist with on-going maintenance. The crew planned the lift using a single sling, as standard lifting strops were missing.

The single sling was placed around the box section and it was identified that the lift point had a sharp edge which could have damaged the lifting sling. 

It was decided to pad the sharp edge with wadding to prevent damage to the sling. The crane started to take the weight of the trencher, and when it reached approximately 18T of tension, the sling failed. 

Upon inspection, it was found that the sharp edge identified had cut through the padding and sliced the sling causing it to part under load. No damage occurred as the trencher was never lifted off the ground.

Initial lifting point arrangement used during incident

initial lifting point arrangement used during incident

re-assessed lifting point arrangement used after incident

Re-assessed lifting point arrangement used after incident

What were the causes?

Our member identified the following immediate causes:

  • Inadequate planning – other lift points were available to complete the lift without the sharp edge affecting the lift.

  • No management of change or ‘stop the job’ completed – the ‘stop the job’ process should have been implemented as soon as the missing strops were identified.

  • Planned method continued despite identification of sharp edge – crew assumed that padding the sharp edge would be sufficient to complete the lift safely.

  • No specific planned method was identified for completion of the lifts – planning was completed at site as requirements developed.

Our member identified the following root causes:

  • Inadequate equipment available:

    • There was insufficient lifting equipment to complete the assigned tasks, leaving the crew to borrow equipment from elsewhere; the job should have been stopped in this context;
  • Poor pre-work planning:

    • There was no lift plan developed before arrival at site.

    • Correct lift points were not identified.

    • Lift plan was developed at site developed with available rigging in mind, rather than correct lift points in mind.

  • Lack of situational awareness

    • All aspects of health and safety planning were completed, as required with regards to lift plans, job safety analysis and tool-box talk; however, an assumption was made regarding the application of padding around the sharp edge.

Lessons learnt

The following lessons were learnt:

  • Ensure sufficient and appropriate lifting equipment is always available.

  • Reiterate importance of ‘stop the job’ and management of change processes.

  • Ensure lift planning is conducted with reference to correct and safe lifting, rather than ‘making do’ with what is available on site;

Members may wish to refer to Guidelines for lifting operations for further information.

Latest Safety Flashes:

LTI: Finger injury during emergency recovery of ROV

A worker suffered a serious finger injury when their finger was caught between a crane wire and the recovery hook on an ROV.

Read more
BSEE: recurring hand injuries from alternative cutting devices

The United States Bureau of Safety and Environmental Enforcement (BSEE) has published Safety Alert 487.

Read more
NTSB: Crane wire failure

The National Transportation Safety Board of the United States (NTSB) published "Safer Seas Digest 2023".

Read more
Hot work performed outside of Permit to Work (PTW) boundary limit

A near miss occurred when a third-party contractor working removed a trip hazard from the vessel main deck, using a cutting torch and grinding disc.

Read more
Vital safety information (height of vehicle) found incorrect

“Height of vehicle” information displayed on a truck, was found to be incorrect.

Read more

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of the entire offshore industry.

The effectiveness of the IMCA Safety Flash system depends on the industry sharing information and so avoiding repeat incidents. Incidents are classified according to IOGP's Life Saving Rules.

All information is anonymised or sanitised, as appropriate, and warnings for graphic content included where possible.

IMCA makes every effort to ensure both the accuracy and reliability of the information shared, but is not be liable for any guidance and/or recommendation and/or statement herein contained.

The information contained in this document does not fulfil or replace any individual's or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.

Share your safety incidents with IMCA online. Sign-up to receive Safety Flashes straight to your email.