IMCA decommissioning principles in relation to DISMANTLECON

  • Informative Guidance
  • Revision 0.1 - December 2020

 

This document outlines IMCA's decommissioning principles in relation to the new BIMCO Dismantling, Removal and Marine Services Agreement (DISMANTLECON), emphasising the alignment with IMCA's decommissioning contracting principles.

Contents

  • Introduction

  • Principles in relation to DISMANTLECON

    • Company Group and Contractor Group property and personnel

    • Project works (including both Company- and Contractor-supplied items)

    • Title

    • Duty holder

    • Company provided information

    • Permits and licences

    • Pollution and contamination

    • Third parties

    • Consequential losses

    • Gross negligence and wilful misconduct

    • Warranty obligations

    • Limitation of liabilities

    • Minimum insurance requirements

    • Force majeure and suspension

    • Delay

    • Variation orders

    • Free access to work site

    • Intellectual property rights

    • Termination by company for convenience

    • Company’s obligation to pay contractor

    • Operating permits and permits to work

    • Extraordinary risk

    • Anti-corruption

  • Summary


Revision

  • Rev. 0.1 - June 2024
    Page 2, template and bookmarking updated; no change to content
  • Rev. - December 2020
    Initial publication