High voltage breaker trip
- DP Event
- Published on 10 August 2017
- Generated on 1 November 2026
- DPE 03/17
- 2 minute read
Observation
Jump to:
One of the wires from a breaker had chaffed on the inside of the box resulting in a short and evidence of arcing to ground.
Comments
Investigation started at the breaker for DG No.5 in the port switchgear room.
The breaker showed tripped and there was a fault present on the auto voltage regulator (AVR). DG No.5 was locked out and investigation continued, the AVR breaker ‘S1’ was found tripped. Further investigating found that one of the wires from this breaker had chaffed on the inside of the box and resulted in a short and evidence of arcing to ground. The damaged wires were replaced and the rest of the wires in the junction box adjusted to avoid future problems.
After replacing the worn wires and test running the engine it was noticed that the load indicator on the PMS panel was showing a negative reading, which was incorrect. This signal was a feedback from the breaker module and was in fact sending a false milliamp signal to the PMS. Racked the breaker out to perform a hard reset, the kilowatt signal from the relay went to zero.
DG No.5 was run, tested and connected to the 11kV bus, all in proper working order.
Considerations
- The investigation explained that the AVR breaker trip caused the DG No.5 breaker to open presumably as a result of a reactive power (kVar) protection scheme. It seems from the investigation notes that there wasno connection between the original fault and the negative active power (kW) signal.
- Similar wire checks should be made on all other engines.
- Having four DGNSS enabled in the DP controller is not a good practice as the total ‘DGNSS weight’ is reducing the ‘acoustic weight’ to insignificant.
- The DP alert status should be initiated in accordance with activity specific operating guidelines.
Latest DP incidents
-
Watch what you are pressing
While transiting away from a wind farm, the Master of a DP equipment class 2 vessel observed that the vessel was operating in Backup Mode and queried this with the bridge team and attending electrician
DPE 03/26
19 October 2026
Incident
-
The domino effect
The event demonstrates the importance of maintaining the approved DP power configuration, addressing known defects before equipment is relied upon during DP operations, and ensuring DP personnel understand how changes to the generating arrangement can affect redundancy and failure propagation
DPE 03/26
19 October 2026
Incident
-
Lost in calibration
During activity associated with calibration of a vessel Vertical Reference Unit (VRU), the DP control system experienced degradation of its attitude reference arrangement. Shortly afterwards, the vessel generated an Off Position Warning followed by an Off Position Alarm
DPE 03/26
19 October 2026
Incident
-
The UPS and downs
While a vessel was transiting in DP mode, the DPO observed the loss of Gyros 2 and 3 together with alarms from a 230V backup power supply. The telephone system remained powered but was inoperable.
DPE 03/26
19 October 2026
Incident
-
DP drill scenario – Consequence Analysis Class DP2 & DP3
DP drill scenario – Consequence Analysis Class DP2 & DP3
DPE 03/26
19 October 2026
Drill Scenario
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.