Loss of gyro input causes loss of position
- DP Event
- Published on 28 September 2020
- Generated on 13 December 2024
- DPE 03/20
- 4 minute read
Incident
Jump to:
A case study which highlights the importance of conducting daily compass checks and completion of all other operational checklists.
Overview
A DP2 vessel was involved in ROV operations in deep water with good visibility. The environmental conditions were moderate with a wind speed of 15 Knots and a current speed of 1.2 knots during the time of event. The vessel was operating in open bus tie mode with two redundant groups.
There were five thrusters and four generators installed on the vessel and all were selected to DP. There were three gyros, two position reference systems and two wind sensors available and all selected to DP.
The following diagram depicts the system configuration prior to the event:
The event
An alarm “Gyro 2 Not Ready” appeared and gyro 2 was automatically deselected from the DP system. Immediately after this, gyro 1 also dropped out with alarms, “Gyro 1 Not Ready” and “Gyro 1 Heading Dropout”. Within one second the third gyro failed with the following alarms in succession, “Gyro not enabled”, “All Reference systems rejected” and “Position Dropout”.
It was noted that gyro 1 repeater on the bridge continued to display the correct heading, while heading input from gyro 1 was missing at the DP operator station (OS). Concurrently, it was further noticed that gyro 2 repeater was in alarm with no heading display and gyro 3 was displaying the heading with 10 degrees offset. Orders were given to recover the ROVs on deck and the vessel control was transferred to full Manual mode.
The crew managed to get the vessel back to full DP control within twenty-eight (28) minutes from the onset of the first failure with one hundred and fifty (150) metres of uncontrolled movement during that time.
The following actions were executed:
- Gyro 2 restarted, rebooted and realignment completed.
- DP OS 1 & OS 2 soft rebooted.
- Controllers A & B of OS 1 rebooted after which all PRS and DP sensors online and enabled.
The investigation revealed that gyro 2 was lost due to the loss of its Interface and Power Supply Unit. After replacing this unit, a test was carried out to prove the independence of gyro 1 from gyro 2. On disconnecting the power supply to gyro 2, it was observed that gyro 1 was also lost. Further system analysis concluded that the gyro 1 ready signal was linked with that of gyro 2 in the DP controller cabinet. This cross-connection issue caused a detrimental effect on both gyros’ performance. In addition, following a malfunction on any gyro, the No. 1 Control and Display Unit would force the gyro 1 ready signal to disappear at the DP operator station. These issues were corrected and tested to the satisfaction of all involved parties.
During the time of the incident gyro 3 sensor value was found to be approximately ten (10) degrees different from gyro 1 and gyro 2 headings. When both gyros 1 and 2 were deselected from DP, gyro 3 was selected to the DP system. However due to the large deviation in the heading value of gyro 3 compared with the estimated heading, which in this case should not have been more than two degrees, the DP controller rejected gyro 3.
Lessons learned
- If a gyro has a static deviation from other gyros, this should have been identified, investigated, and rectified so that all gyros’ measured headings are within the DP control system limits to avoid any such problems.
- The common mode failure related to the ready signal of gyros’ 1 and 2, should have been identified during commissioning, FMEA proving trials and DP annual trials programme. IMCA documents M166, “Guidance on Failure Modes & Effects Analyses (FMEAs) and M190, “Guidance for Developing and Conducting DP Annual Trials Programmes”, underline the importance of having robust FMEA and set of annual trials.
- IMCA M252 “Guidance on Position Reference Systems and Sensors for DP Operations” provides general information on use of reference systems and the good practice of multiple references and sensors.
- Importance of proper investigations and robust testing of cross connections in redundancy groups of DP vessels is highlighted in this case study.
Conclusions
This case study demonstrates the importance of robust testing procedures during FMEA proving trials, annual trials or five-yearly trials program. The case study also highlights the importance of conducting daily compass checks and completion of all other operational checklists so that differences in redundancy groups are identified early and can be corrected.
Latest DP incidents
-
Prepare for 2025 solar activity
This case study covers events that occurred on the same vessel, eight months apart.
DPE 02/24
29 July 2024
Undesired event
-
Know your vessel capabilities and when to stop!
An incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Duty/not duty, which is the question?
With no steering control of the port azimuth thruster, and no other thrusters operational, the heading of the FPU could not be maintained.
DPE 02/24
29 July 2024
Undesired event
-
You’ve got the ASOG, so now you’ve got to follow it
This case study examines an incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Button trouble
A Dynamically Positioned vessel experienced a loss of Dynamic Positioning (DP) control while installing cable within a wind farm.
DPE 01/24
3 April 2024
Incident
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.