Planned investigation resulted in DP incident
- DP Event
- Published on 18 February 2019
- Generated on 14 December 2024
- DPE 01/19
- 2 minute read
Incident
Jump to:
There was a total loss of network communication affecting many field stations together with loss of DP communication to all thrusters.
Comments
An AVR problem in diesel generator No.1 engine caused an over voltage in the system. Due to increased voltage, the standby machine could not be brought online, and the switchboard required a controlled blackout.
After this, many alarms from Network B were observed due to the supply being interrupted. An hour later, there was a total loss of network communication affecting many field stations together with loss of DP communication to all thrusters, which caused the vessel to drift off.
The probable cause was accidentally resetting network A, when trouble shooting of network B was taking place.
Further investigation of the overvoltage issue found a 3-phase breaker was faulty to engine No.1; the breaker was replaced by an onboard spare. The DP system manufacturer concluded that the vessel was operational as designed, indicating a possible human mistake by rebooting network A.
Considerations
It appears the DP system manufacturer responded well to this event.
The selection of “operator specified turn radius” (radio button selection) should be inhibited and “greyed out” when vessel is in a turn while move-up sub mode is active.
This inhibit function was not activated when the dialog box was opened again after the “auto – turn – move up” function had been activated. Four conditions have to be aligned for this to happen.
The “move-up” mode was introduced in 2002 and this is the first time this was reported to the original equipment manufacturer. So, the MTBF is 15-years but of course the consequence could be damage to the pipe.
A software modification has been made, installed and tested on this specific vessel. The global customer support team have a process in place to go through all software releases which have this function and update the vessels that are affected during next service visit.
Latest DP incidents
-
Prepare for 2025 solar activity
This case study covers events that occurred on the same vessel, eight months apart.
DPE 02/24
29 July 2024
Undesired event
-
Know your vessel capabilities and when to stop!
An incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Duty/not duty, which is the question?
With no steering control of the port azimuth thruster, and no other thrusters operational, the heading of the FPU could not be maintained.
DPE 02/24
29 July 2024
Undesired event
-
You’ve got the ASOG, so now you’ve got to follow it
This case study examines an incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Button trouble
A Dynamically Positioned vessel experienced a loss of Dynamic Positioning (DP) control while installing cable within a wind farm.
DPE 01/24
3 April 2024
Incident
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.