A mechanic had started a deck air compressor, when the sudden delivery of pressurised air through the delivery hose caused momentary snaking of the hose. 

What happened?

The mechanic acted in a calm manner and switched off the compressor immediately. Fortunately no one was positioned close to the coiled hose, so nobody was injured. Nothing was damaged.

The snaking hose had the potential to cause injury to personnel on deck.

During investigation, it was also noticed that the isolation valve’s handle was missing.

Before starting the compressor, the mechanic had not checked the delivery valves to confirm that these were closed. The missing valve handle had not been reported.

The company involved has issued a safety reminder to its personnel as follows:

World-wide, many serious accidents occur due to snaking hoses. It is, therefore, necessary to follow some simple safety precautions before and during use of any compressor:

  • Before starting up a compressor, ensure that all air delivery valves are shut
  • Check that all valve handles are secured in place
  • Check condition of hose for any physical damage
  • Check all hose line clamps for tightness, to ensure non inadvertent parting of hoses while in use
  • Check all hose connections are secured with safety rope, to prevent a whiplash/snaking effect if parted
  • Ensure insurance wire is fixed on all quick-release couplings to prevent inadvertent parting of couplings while in use
  • Ensure all hose lines are anchored/secured with rope to fixed structures, to prevent a whiplash effect if parted
  • Know where the compressor’s ’emergency stop’ button is situation and how to use it
  • After use, ensure that air-delivery valves are closed and that the delivery hose is coiled and kept safely
  • Report all unsafe acts and unsafe conditions.

Latest Safety Flashes:

SWL plate dropped from crane block

An “SWL” plate weighing 0.9kg fell from the auxiliary hook block and landed on the main deck of a newly purchased vessel.

Read more
Unsafe Lifting practices during dry dock

An unsafe attempt was made to lift 14 empty oil drums using only a web sling, without clamps, certified frames, or proper securing.

Read more
Handling alarms on the bridge – a DP incident

DPO accidentally pressed the adjacent "Take" button on the DP panel.

Read more
Uncoordinated Emergency Shutdown due to pipe failure

All cargo pumps (No. 1, 2, and 3) tripped simultaneously due to Emergency Shutdown (ESD) activation.

Read more
UK HSE: oil company fined after serious failure of elevator

The UK HSE has fined a North Sea oil and gas operator £300,000 after three crew members descended into a water filled lift shaft on a floating platform in the North Sea causing them to become partially submerged.

Read more

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of the entire offshore industry.

The effectiveness of the IMCA Safety Flash system depends on the industry sharing information and so avoiding repeat incidents. Incidents are classified according to IOGP's Life Saving Rules.

All information is anonymised or sanitised, as appropriate, and warnings for graphic content included where possible.

IMCA makes every effort to ensure both the accuracy and reliability of the information shared, but is not be liable for any guidance and/or recommendation and/or statement herein contained.

The information contained in this document does not fulfil or replace any individual's or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.

Share your safety incidents with IMCA online. Sign-up to receive Safety Flashes straight to your email.