- Enter the IMCA Awards 2024: We\'re looking for outstanding Safety, Sustainability, and GHG projects.
- IP Code: Mandatory Code enters into force on 1 July. Make sure your company is up to speed with the changes.
- Early Bird tickets available for the IMCA Global Summit 2024. 3-4 December, Utrecht, Netherlands. Members can save £400.
- Discover how we are helping Members reduce emissions: Explore the ProjectGHG hub now.
- Now booking. Join the Lifting and Rigging community at our Technical Seminar in Amsterdam. Thursday 12 September 2024
- Now booking. Underwater Ship Husbandry Seminar. 10 October 2024, Singapore.
Wire inserts in anchor line parted
A member has reported an incident in which wire inserts parted in two anchor lines of a semi-submersible accommodation unit connected to a fixed platform during extreme weather conditions (9 m seas, 70 knot winds). Non-essential personnel were taken off the semi-submersible accommodation unit until the mooring system could be safely recovered and replaced.
During recovery of the mooring system it was discovered that the wire inserts in both the affected mooring lines had slipped out of the socket at the rig end. The wire inserts were taken ashore for investigation.
Following investigation the following was noted:
- the failed wire inserts had not been moulded on to the sockets using proper procedures;
- the supplier of the failed wire inserts was not aware of the procedure and its personnel were not formally trained in the moulding operation;
- the supplier of the wire inserts and other contract-specific anchoring equipment had not been audited by this or any other customer;
- similar incidents regarding wires slipping out of sockets had occurred but had not been brought to public attention;
- there was a detailed investigation of the design of the mooring system. The system used mooring lines supported by buoys, but it was not possible to ascertain that this was directly causative.
The company recommended the following:
- higher awareness of procedures for moulding sockets on to wires and increased training for personnel engaged in such work to ensure that personnel involved are properly qualified for the work;
- audit of suppliers of contract specific mooring equipment for appropriate quality management system;
- free sharing of similar incidents to prevent recurrence of incident;
- research into testing wires with moulded sockets.
Safety Event
Published: 14 August 2007
Download: IMCA SF 07/07
IMCA Safety Flashes
Submit a Report
IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding [email protected] to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.
IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.
IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.