DP Drill Scenario
- DP Event
- Published on 16 January 2025
- Generated on 8 May 2025
- DPE 01/25
- 4 minute read
Drill Scenario
Refer to IMCA M117 Code of practice for the training & experience of key DP personnel, Appendix 6.
Exercise Scenario AUTO/MANUAL – Human Intervention |
ObjectiveTo familiarise all vessel crew what the consequences of switching essential DP equipment into Local/manual whist in auto DP. There have been many event reports submitted that have detailed the effects of switching running equipment into local/manual, mainly because the effects of doing so were unknown, carrying out this drill will enable the Key DP Personnel to further understand the consequences of their actions. |
MethodThis test can be undertaken when the vessel is in a safe open space with no risk of excessive position excursion causing an unsafe condition. Vessel in auto DP 1 Thrusters
2 Engines
3 Pumps
At local position, switch running fuel pump into local – Observe effect on SW system – Reinstate. 4 DP ControllersOn running/in use controller, reset – Observe effect on DP control – Reinstate |
Observations During Drill
|
Discussion Points (Post-exercise)
|
ConclusionBased on the results of the exercise and related discussions before and after, any suggestions for follow up including any corrective actions deemed appropriate should be accurately detailed and managed to close out. Handling of essential DP systems in the correct manner requires knowledge of the Key DP Personnel and how the DP system reacts to human intervention. Items to consider include:
|
Latest DP incidents
-
Complete the job
Whilst connected to a turbine, an alarm was generated on the DP operator station, ‘Unbalanced load on SWBD 1’.
DPE 01/25
16 January 2025
Undesired event
-
Beware your centre of rotation
The stern thrusters started to oscillate which transferred to an oscillating motion of the vessel and high forces were being used to try to maintain position.
DPE 01/25
16 January 2025
Incident
-
A-Tension
Whilst pipelaying in shallow water, the vessel experienced a tension sensor failure on one tensioner.
DPE 01/25
16 January 2025
-
How is your alignment?
Loss of the CyScan position reference system generated a reference system failure alarm and moments later the vessel began to lose position with the accompanying alarms.
DPE 01/25
16 January 2025
Incident
-
DP Drill Scenario
DP emergency drill scenarios are included to assist DP vessel management, DPOs / Engineers, and ETOs in conducting DP drills onboard.
DPE 01/25
16 January 2025
Drill Scenario
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.