Lack of planning and situational awareness
- DP Event
- Published on 2 November 2017
- Generated on 23 June 2025
- DPE 04/17
- 2 minute read
Incident
Jump to:
In such critical subsea operations both DPOs should have been 100% focused on current operations.

Comments
The event was investigated by the vessel operator, findings are summarised below:
Human factors:
- The DPO was left alone at the DP console during critical subsea operations. In such critical subsea operations, subsea lifting in vicinity of Christmas tree, both DPOs should have been 100% focused on current operations.
- Following the power limitation alarms, the DPO didn’t inform the SDPO, or request to start additional generators. Despite having wind and current pushing the vessel in the direction of the Christmas tree, he didn’t realise that the situation was becoming critical.
Processes and procedures:
- The activity specific operating guidelines (ASOG) was built up considering only vessel operations criticality and location (inside or outside the 500m zone), it failed to take into consideration the power consumption of ROV and cranes during these operations.
- The ASOG required only 2 DG on each bus bar. That means that YELLOW status (load >50%) would be reached earlier than with 3 DG per bus bar. The DPO and engineer on watch didn’t respect the ASOG as they didn’t react when YELLOW status was reached.
Equipment and design:
- The purpose of a micrologic breaker is to protect the electrical circuit from damage caused by excess current. In this situation, the breaker interrupted current due to misreading of the amperage. Preventive maintenance routines had been followed and increasing maintenance frequency would not prevent the kind of failure that affected DG No.5.
Considerations
- The power limitation alarm was active for 11 minutes, the power management system did not instigate an automatic start, therefore the FMEA and DP trials should be questioned.
- Neither the DPO nor engineer reacted to the situation and one DPO was left alone at the DP control station during a critical phase.
- Lack of preplanning and development of a separate ASOG for the task directly contributed to the event.
- The vessel is recorded as operating within DP equipment class 2, however only satellite derived position reference systems were recorded as being in use.
Latest DP incidents
-
Complete the job
Whilst connected to a turbine, an alarm was generated on the DP operator station, ‘Unbalanced load on SWBD 1’.
DPE 01/25
16 January 2025
Undesired event
-
How is your alignment?
Loss of the CyScan position reference system generated a reference system failure alarm and moments later the vessel began to lose position with the accompanying alarms.
DPE 01/25
16 January 2025
Incident
-
Beware your centre of rotation
The stern thrusters started to oscillate which transferred to an oscillating motion of the vessel and high forces were being used to try to maintain position.
DPE 01/25
16 January 2025
Incident
-
A-Tension
Whilst pipelaying in shallow water, the vessel experienced a tension sensor failure on one tensioner.
DPE 01/25
16 January 2025
-
DP Drill Scenario
DP emergency drill scenarios are included to assist DP vessel management, DPOs / Engineers, and ETOs in conducting DP drills onboard.
DPE 01/25
16 January 2025
Drill Scenario
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.