Commissioning and verification of newly installed modified diving system equipment

  • Safety Flash
  • Published on 1 January 2000
  • Generated on 13 December 2024
  • IMCA SF 01/00
  • 2 minute read

One of our members has recently experienced a very serious near-miss when the recovery of a diving bell was started accidentally and unintentionally prior to the bell door being closed and secured.

What happened?

On investigating the near-miss, it was found that a modification to the bell winch hydraulic and electrical systems had taken place on this newly-installed diving system and that vital parts of both the primary and emergency systems, including the emergency stops, were not functioning correctly.

Although the dive system had been installed and verified in accordance with the principles and checklist contained in IMCA guidance note AODC 052 –Diving Equipment Systems Inspection Guidance Note (DESIGN) – no test protocol had been developed or used in this instance during the final acceptance test of the modified winch hydraulics and control system. The acceptance test could thus not be verified or documented.

Recommendations

To avoid a similar situation occurring in future, the following instructions have been issued by the contractor and applies to installation, commissioning and testing of newly installed or modified diving system equipment:

  • Equipment which is to be installed or has been modified thereafter should meet the principles of DESIGN and/or any other applicable industry standards, codes of practice, etc.
  • Responsibility for the installation or modification and testing of the equipment should be clearly defined.
  • Any changes to the dive system configuration should be assessed for the implications of the changes before any work is carried out.
  • A test protocol for the testing and verification of the system – and its individual sub-systems – should be developed and should include ‘as-built’ drawings/schematics of all vital sub-systems. Relevant equipment operating procedures should also be developed.
  • The test protocol and associated ‘as-built’ drawing/schematics should be used as a tool during final acceptance test and hand over to the operations team. The test should be conducted by a competent person and witnessed by an appropriate supervisor. Both parties should normally sign the test protocol and any unexpected findings recorded. The test protocol should, once signed, form part of the system documentation and be kept in the dive system certification file

Latest Safety Flashes:

LTI: Finger injury during emergency recovery of ROV

A worker suffered a serious finger injury when their finger was caught between a crane wire and the recovery hook on an ROV.

Read more
BSEE: recurring hand injuries from alternative cutting devices

The United States Bureau of Safety and Environmental Enforcement (BSEE) has published Safety Alert 487.

Read more
NTSB: Crane wire failure

The National Transportation Safety Board of the United States (NTSB) published "Safer Seas Digest 2023".

Read more
Hot work performed outside of Permit to Work (PTW) boundary limit

A near miss occurred when a third-party contractor working removed a trip hazard from the vessel main deck, using a cutting torch and grinding disc.

Read more
Vital safety information (height of vehicle) found incorrect

“Height of vehicle” information displayed on a truck, was found to be incorrect.

Read more

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of the entire offshore industry.

The effectiveness of the IMCA Safety Flash system depends on the industry sharing information and so avoiding repeat incidents. Incidents are classified according to IOGP's Life Saving Rules.

All information is anonymised or sanitised, as appropriate, and warnings for graphic content included where possible.

IMCA makes every effort to ensure both the accuracy and reliability of the information shared, but is not be liable for any guidance and/or recommendation and/or statement herein contained.

The information contained in this document does not fulfil or replace any individual's or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.

Share your safety incidents with IMCA online. Sign-up to receive Safety Flashes straight to your email.