Lift bag near miss

  • Safety Flash
  • Published on 13 March 2023
  • Generated on 7 October 2026
  • IMCA SF 07/23
  • 3 minute read

During the over-boarding of a spool, a lift bag while being inflated, ascended through the engineered rigging arrangement and was caught by the contingency rigging.

What happened?

The diver had rigged the lift bag inappropriately for the conditions.

The lift bag was hooked into one eye of the sling, the sling then slipped out as the lift bag became inflated and was inverted with the safety strap.

Our member considered this incident to have had the potential for a serious injury or fatality.

Spools were being rerigged subsea to gain the third wrap needed for the lift bag attachment

Spools were being rerigged subsea to gain the third wrap needed for the lift bag attachment

 

What went wrong?

  • Assumptions were made by the diver and by the supervisor, about the rigging, perhaps owing to:

    • poor visibility

    • diver inexperience with lift bag operations

    • complacency.

  • The rigging arrangements were not correct nor verified as per procedure:

    • Spool rigging and local in-field adjustment began to happen without proper documentation or formal management of change (MoC).

    • The divers were multi-tasking, working in different locations on different concurrent tasks, and communications between the divers and diver supervisor were complex and unclear.

    • The rigging had been changed earlier but this change had not been communicated to the dive team.

    • As the final spool was lowered, late at night, rigging changes were not noticed.

  • Existing procedures were not specific to this task:

    • A 4-ton lift bag was identified in the procedure but was not available.

    • The inverter rigging was not one size fit all, as the bags were different sizes, thus creating a scenario where diver rigging was required to lengthen or shorten the existing rigging.

  • There were changes of personnel during the job:

    • Superintendents were changed out.

    • The bell run was split such that the diver that de-rigged the spool was not the same diver as inflated the lift bag that came loose.

  • During the job, a finger incident occurred on the bell clump basket, and there was a safety stand down.
Black Duct Tape added to “hold” the rigging in place

Black duct tape added to “hold” the rigging in place

 

Lessons learned

  • Ensure one single person is accountable for rigging, reporting to the Superintendent and collaborating with the dive team.

  • Improve management and installation of rigging configurations.

  • Ensure written procedures are not generic, are up to date, and reflect the details of the task in hand.

  • Minimise multitasking to eliminate distractions and fatigue.

  • Be additionally vigilant and ensure there is thorough communication:

    • at crew change and at shift change

    • between shore-side or yard and vessel

    • between crew of different departments – dive, deck, bridge, project, etc.
Note the middle leg is not choked, as per the drawing,  change not noticed, nor articulated to the divers

Note the middle leg is not choked, as per the drawing, change not noticed, nor articulated to the divers

 

Latest Safety Flashes:

Hydraulic oil leak detected below moonpool

A hydraulic oil leak was identified below the moonpool after the worktable doors were opened.

Read more
Dropped scaffold board (kickplate) – SIF near miss

A scaffolding kickboard was accidentally dropped falling from a height of 6.5 metres to the main deck.

Read more
H₂S detected on deck

During vessel transit back to port, Hydrogen Sulphide (H₂S) was detected in the open space on the main deck.

Read more
Restoration and verification after maintenance

A missing flooring panel was identified beneath a 415V bow thruster electrical motor cabinet.

Read more
Vessel contact during materiel transfer in adverse weather

One vessel lost heading and position control because of the strong winds and swell, pushing it toward another.

Read more

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of the entire offshore industry.

The effectiveness of the IMCA Safety Flash system depends on the industry sharing information and so avoiding repeat incidents. Incidents are classified according to IOGP's Life Saving Rules.

All information is anonymised or sanitised, as appropriate, and warnings for graphic content included where possible.

IMCA makes every effort to ensure both the accuracy and reliability of the information shared, but is not be liable for any guidance and/or recommendation and/or statement herein contained.

The information contained in this document does not fulfil or replace any individual's or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.

Share your safety incidents with IMCA online. Sign-up to receive Safety Flashes straight to your email.