- Enter the IMCA Awards 2024: We\'re looking for outstanding Safety, Sustainability, and GHG projects.
- IP Code: Mandatory Code enters into force on 1 July. Make sure your company is up to speed with the changes.
- Early Bird tickets available for the IMCA Global Summit 2024. 3-4 December, Utrecht, Netherlands. Members can save £400.
- Discover how we are helping Members reduce emissions: Explore the ProjectGHG hub now.
- Now booking. Join the Lifting and Rigging community at our Technical Seminar in Amsterdam. Thursday 12 September 2024
- Now booking. Underwater Ship Husbandry Seminar. 10 October 2024, Singapore.
Fall from height – LTI
What happened?
On a vessel that was alongside, crew were engaged in offloading equipment from below-decks through a series of hatches, when their supervisor lost his footing and fell through the hatches, falling 7m. He was taken to hospital with a dislocated and fractured shoulder and a broken ankle. The ankle injury required surgery, and physiotherapy over a number of months before he was fit to return to work.
What went wrong?
A portable barrier (two stanchions and length of chain) was put around the area to warn of a trip hazard. This was because although it was closed, the hatch was not fully sea-fastened.
Recovery to deck of the equipment could be conducted without use of the vessel crane, and the crew held a Toolbox Talk and Pre-Task Assessment before starting, to discuss the method of lifting between the two decks using two chain pulls joined together.
Crew operating the chain pulls were stood inside the barriered off area, wearing fall arrest harness and inertia reel. Their supervisor was on the upper main deck outside of the barriered off area. As the equipment was being lifted using this technique, he moved to get a better look at what was happening. As he did so, he lost his footing and tipped forward toward the portable barrier stanchions and chain, and fell through the barrier and down the hatch.
What were the causes of the incident? Causal factors identified:
- Fall prevention barriers that were around the upper main deck hatch were not suitable or sufficient. There was insufficient robust barrier hardware available on board;
- Several trip hazards existed around the area:
- where the task was being carried out
- where the Supervisor was standing
- where the portable barrier was previously positioned – this was also close to the edge of the open upper main deck hatch;
- The Supervisor was too close to open hatch hazards without sufficient fall protection;
- visual obstruction prompted the Supervisor to move to get a better look at the activities he was supervising. In so doing he knocked against the portable barrier
- the supervisor lost his footing/balance close to the edge of the portable barrier and open deck hatches;
- A generic or blanket Permit to Work was used for the recovery/lifting of this equipment using a working at height/chain pull method, rather than a specific Permit to Work.
What lessons were learnt?
- Time spent discussing the lift in detail, may have detracted from proper review of the suitability of the existing barrier, and possibly divided attention over risks from the lift versus that from the fall;
- Better management required of Permit to Work system for specific and non-routine tasks;
- A proper review of the barrier previously put in place, and its adequacy to protect against falls versus highlighting a potential trip hazard, seems to have been forgotten during the planning stages of the task;
Lapses do happen – Comprehensive checklists to confirm specific actions required can help address potential lapses. These checklists could be included in pre-task dynamic/situational assessment, and standard pre-start checks made within the Permit to Work process.
Members may wish to refer to the following incidents:
Safety Event
Published: 13 July 2017
Download: IMCA SF 17/17
IMCA Safety Flashes
Submit a Report
IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of all. The effectiveness of the IMCA Safety Flash system depends on Members sharing information and so avoiding repeat incidents. Please consider adding [email protected] to your internal distribution list for safety alerts or manually submitting information on incidents you consider may be relevant. All information is anonymised or sanitised, as appropriate.
IMCA’s store terms and conditions (https://www.imca-int.com/legal-notices/terms/) apply to all downloads from IMCA’s website, including this document.
IMCA makes every effort to ensure the accuracy and reliability of the data contained in the documents it publishes, but IMCA shall not be liable for any guidance and/or recommendation and/or statement herein contained. The information contained in this document does not fulfil or replace any individual’s or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.