DP event investigation and testing inside the 500m zone
- DP Event
- Published on 29 March 2017
- Generated on 14 December 2024
- DPE 01/17
- 1 minute read
Incident
Jump to:
The vessel should have proceeded out of the 500m zone to a safe area prior to investigating the fault and conducting tests.
Comments
The report concluded that the vessel should have proceeded out of the 500m zone to a safe area prior to investigating the fault and conducting tests.
Considerations
- There is no doubt that in circumstances such as this, where investigation and testing is required following a DP event, it should be conducted in a safe location and as a minimum outside the 500m zone.
- The DP system’s level of redundancy always needs to be considered during investigation and testing.
- It is not evident from the report, but it is wondered whether complacency contributed to this bad practice.
- The original reported DP alarm should have resulted in a DP yellow alert.
- The vessel might have considered using the independent joystick (IJS) rather than individual levers.
- Emergency handling of the vessel should be practised on a regular basis.
Latest DP incidents
-
Prepare for 2025 solar activity
This case study covers events that occurred on the same vessel, eight months apart.
DPE 02/24
29 July 2024
Undesired event
-
Know your vessel capabilities and when to stop!
An incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Duty/not duty, which is the question?
With no steering control of the port azimuth thruster, and no other thrusters operational, the heading of the FPU could not be maintained.
DPE 02/24
29 July 2024
Undesired event
-
You’ve got the ASOG, so now you’ve got to follow it
This case study examines an incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Button trouble
A Dynamically Positioned vessel experienced a loss of Dynamic Positioning (DP) control while installing cable within a wind farm.
DPE 01/24
3 April 2024
Incident
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.