Inadequate communication and planning causes fouled thruster
- DP Event
- Published on 29 March 2017
- Generated on 16 May 2026
- DPE 01/17
- 1 minute read
Undesired event
Jump to:
They did not realise they were isolating the opposite thruster and consequently the thruster closest to the lay chute was still running.
Comments
During the over boarding of the end termination through the starboard aft chute, the cable laying shift supervisor asked the bridge to isolate thruster No.5 (port quarter) instead of thruster No.6 (starboard quarter).
They did not realise they were isolating the opposite thruster and consequently the thruster closest to the lay chute was still running. Moreover, they asked the bridge to move backwards and in the same direction where the end termination was being laid down. This movement contributed to the end termination deployment rope fouling thruster No.6.
Considerations
- There was either a lack of operational planning or it was inadequate.
- The event highlights the need for accurate and verified communication between key control centres.
- With three satellite derived position systems on line and the acoustic system on standby the vessel was not complying with the requirements of IMO Circular 645.
Latest DP incidents
-
Think twice. Press once!
On a DP equipment class 2 supply vessel engaged in drilling, an incident occurred due to lack of operational knowledge
DPE 01/26
11 May 2026
Incident
-
Network issues, not a thing of the past
A DP equipment class 3 vessel was engaged in saturation diving activities, with two divers in the water when this DP incident occurred.
DPE 01/26
11 May 2026
Incident
-
All swept up
A DP equipment class 2 vessel was engaged in rock placement operations, within close proximity to a structure, when this event occurred.
DPE 01/26
11 May 2026
Undesired event
-
Hybrid system won't accept load
A DP equipment class 2 vessel was engaged in operations whilst holding position on auto DP, when this undesired event occurred
DPE 01/26
11 May 2026
Undesired event
-
DP drill scenario – Loss of main DP system UPS
The objective of this scenario is to identify risks and impacts of losing the main DP system uninterruptible power supply, possibilities to reduce that risk and suitable actions to be taken if such an occurrence happened.
DPE 01/26
11 May 2026
Drill Scenario
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.
IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.
Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.