Unreliable component causes an undesired event

  • DP Event
  • Published on 25 February 2020
  • Generated on 4 December 2024
  • DPE 01/20
  • 1 minute read

Undesired event

Though redundancy is a must in DP 2/3 designs, component quality may impact the likelihood of such DP events occurring.

DPE 20.01 – Unreliable component causes a DP undesired event – Flowchart

Comments

Investigation found that a 24v bridge rectifier supplying voltage to the main generator switchboard breakers one and two had burned out.

The age and quality of the rectifier was thought to be the main reason for failure. Planned maintenance routines were updated and shared with the fleet. It was recognised that the system was vulnerable due to a single 24v bridge rectifier supplying the entire port switchboard.

Considerations

The vessel validated that it could maintain position following the worst-case failure of a complete switchboard. Though redundancy is a must in DP 2/3 designs, component quality may impact the likelihood of such DP events occurring.


The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.

IMCA makes every effort to ensure both the accuracy and reliability of the information, but it is not liable for any guidance and/or recommendation and/or statement herein contained.

Any queries should be directed to DP team at IMCA. Share your DP incidents with IMCA online. Sign-up to receive DP event bulletins straight to your email.