Unreliable component causes an undesired event
- DP Event
- Published on 25 February 2020
- Generated on 4 December 2024
- DPE 01/20
- 1 minute read
Undesired event
Jump to:
Though redundancy is a must in DP 2/3 designs, component quality may impact the likelihood of such DP events occurring.
Comments
Investigation found that a 24v bridge rectifier supplying voltage to the main generator switchboard breakers one and two had burned out.
The age and quality of the rectifier was thought to be the main reason for failure. Planned maintenance routines were updated and shared with the fleet. It was recognised that the system was vulnerable due to a single 24v bridge rectifier supplying the entire port switchboard.
Considerations
The vessel validated that it could maintain position following the worst-case failure of a complete switchboard. Though redundancy is a must in DP 2/3 designs, component quality may impact the likelihood of such DP events occurring.
Latest DP incidents
-
Prepare for 2025 solar activity
This case study covers events that occurred on the same vessel, eight months apart.
DPE 02/24
29 July 2024
Undesired event
-
Know your vessel capabilities and when to stop!
An incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Duty/not duty, which is the question?
With no steering control of the port azimuth thruster, and no other thrusters operational, the heading of the FPU could not be maintained.
DPE 02/24
29 July 2024
Undesired event
-
You’ve got the ASOG, so now you’ve got to follow it
This case study examines an incident that occurred on an equipment class 2 MODU, during well intervention operations.
DPE 02/24
29 July 2024
Incident
-
Button trouble
A Dynamically Positioned vessel experienced a loss of Dynamic Positioning (DP) control while installing cable within a wind farm.
DPE 01/24
3 April 2024
Incident
The case studies and observations above have been compiled from information received by IMCA. All vessel, client, and operational data has been removed from the narrative to ensure anonymity. Case studies are not intended as guidance on the safe conduct of operations, but rather to assist vessel managers, DP operators, and technical crew.