Near-miss: Unauthorised release of shore-controlled mooring lines

  • Safety Flash
  • Published on 17 July 2014
  • Generated on 16 May 2026
  • IMCA SF 13/14
  • 3 minute read

A member has reported a near miss incident in which mooring lines were released from shore without permission from the vessel bridge. 

What happened?

The incident occurred when the vessel started singling up her mooring lines for departure from a shipyard. The vessel was loaded with a module, which restricted the view aft from the bridge. The vessel was moored ‘Mediterranean style’, including her stern, with two bow anchors, six wire ropes and two conventional mooring lines. Four of the six wire ropes were under shore control.

When the crew of the vessel (with pilot on board) started to single up her mooring lines, the four wire ropes under shore control at the aft side of the vessel were simultaneously released by shore side personnel. This was done without permission from the bridge, when the tugs were not yet in position. This release of the mooring lines could not be observed from the bridge. The bridge was notified with some delay by an additional lookout aft of the vessel. By swiftly ordering propulsion astern, the vessel master avoided heavy stress and possible breakage of the two remaining mooring lines. The vessel remained under control and a tug was made fast before releasing the remaining two mooring lines.

There were no injuries, damage to assets or uncontrolled vessel movements, owing to the swift and effective action from the vessel master.

Our member’s investigation revealed the following:

  • A pre-departure meeting with all involved parties was carried out two days prior departure. Due to adverse weather, it was clearly stated at that meeting that the vessel would single up line by line.
  • Proper precautions were taken, such as hazard identification (HAZID), toolbox meetings and Job Safety Analyses, mooring/unmooring plans.
  • Actual departure was delayed by last minute modification works on the cargo.
  • The vessel master repeatedly refused to start to single up as the gangway was still in place due to delayed works on the cargo.
  • The release of the shore side mooring lines was not stopped by the vessel’s superintendent.
  • The vessel’s superintendent was not equipped with a radio. It was agreed to communicate by mobile phone.

Following the incident, our member drew the following conclusions and recommendations:

  • The last minute modification works on the module and the resulting delay of departure were improperly and ineffectively communicated to and between parties involved. The delay resulted in a change, for which Management Of Change procedures should have been followed in order to effectively prevent the incident as occurred.
  • Reliance on mobile cell phones for operations is inadequate. All responsible parties should communicate by radio with an agreed protocol.
  • Effective and immediate communication between the vessel master and the vessel superintendent is a vital and critical safety factor during such operations and should be catered for accordingly in project execution plans.
  • The shore-based linesmen provided by the shipyard clearly demonstrated a lack of awareness of the risks involved. To lower these risks, when employing third-party personnel for critical operations, the qualifications and training of those personnel involved should be prominently addressed and audited beforehand in project HSE plans.

Latest Safety Flashes:

Worker suffered crush injury while handling unstable steel plates

Steel plates suddenly toppled over to the side trapping a worker's left hand and wrist between a frame and an emergency stop pedestal.

Read more
High Potential Near Miss: Dropped object due to contact with crane sheave

A Dynamic Positioning (DP) beacon came into contact with sheave protection bars, resulting in the beacon and its holder assembly detaching and falling to the deck below.

Read more
Machinery damaged through improper maintenance technique

During an audit on an offshore vessel it was observed that the fuel oil purifier failed to self-discharge.

Read more
Shifting cargo and deck spill during heavy weather

A sodium chloride brine storage tank shifted approximately 0.5m during heavy weather conditions.

Read more
MSF: Fast Rescue craft (FRC) washed overboard and lost at sea

The Marine Safety Forum (MSF) has published Safety Alert 26-03 relating to the loss of a Fast Rescue Craft (FRC).

Read more

IMCA Safety Flashes summarise key safety matters and incidents, allowing lessons to be more easily learnt for the benefit of the entire offshore industry.

The effectiveness of the IMCA Safety Flash system depends on the industry sharing information and so avoiding repeat incidents. Incidents are classified according to IOGP's Life Saving Rules.

All information is anonymised or sanitised, as appropriate, and warnings for graphic content included where possible.

IMCA makes every effort to ensure both the accuracy and reliability of the information shared, but is not be liable for any guidance and/or recommendation and/or statement herein contained.

The information contained in this document does not fulfil or replace any individual's or Member's legal, regulatory or other duties or obligations in respect of their operations. Individuals and Members remain solely responsible for the safe, lawful and proper conduct of their operations.

Share your safety incidents with IMCA online. Sign-up to receive Safety Flashes straight to your email.